# Spring 2017 Review
BenoƮt PILORGET
1st Reporting period from Sept. 2015 to February 2017
- Location: Brussels
- Dates: 26th April 2017 (preceded by two days of rehearsals and meetings)
See also the [README](https://github.com/OpenDreamKit/OpenDreamKit/#organization-of-official-meetings)
---
## Tentative agenda
- Day 1: Mock presentations
Just like for the review but without Reviewers
- Day 2: Project meetings
Steering Committe, Quality Review Board, ...
- Day 3: Official Review
- Coding sprints may be added to that
--
## Tentative agenda for the official review
- Presence:
- WP leaders + Coordinator + project manager
- At least one representative per site
- Tentative agenda:
- Welcome and tour de table
- General introduction by the coordinator
- Presentations of deliverables by workpackage:
- WP leader presenting + if necessary deliverable leaders
- Duration per WP: depending of the amount of content to present
--
- Presentation on dissemination, management, and use of resources
- Discussion among the reviewers
- Brief assessment by the reviewers
---
## Advice for WP & Deliv. presentations
Presentations during the review should contain:
- In a slide presentation
- State of the art at beginning of project for the Work Package
- Short and striking story about the relevance and goal of the deliverable
- Give involved partners, estimate resources used (i.e. number of PMs if possible) and how much ODK helped to this result
--
- In the most appropriate format
- What was achieved, by ODK / by the community
- Brief description of current activities, future outcomes and plans
- Any reference to the Proposal is welcome (graphs, WP or deliverable descriptions etc.)
---
## General advice
- You don't have to answer general/administrative questions
Ex: for a question concerning the methodology of an institution, a lab can send the question to the relevant institution administration
- If you are not certain of the answer, do not hesitate to request
time to give clarification
---
## Grades
The Consortium will be graded according to this scale:
- 4/4: Excellent progress (objectives and technical goals for the period fully achieved and even exceeded expectations)
- 3/4: Good progress (most of objectives and technical goals achieved for the period with relatively minor deviations)
- 2/4: Acceptable progress (some of its objectives achieved; however, corrective action will be required)
- 1/4: Unsatisfactory progress (the project has failed to achieve key objectives and/or is not at all on schedule) = project is cancelled
---
## Periodic Reports
- Periodic technical report (coordination team)
- starting point: D1.3's report
- fleshed up to 2-3 pages per work package, typically by giving a
longer description of the deliverables
- Goal: give an exhaustive and concise sum up of the 1st Reporting Period results
- Periodic financial report (UPSud finance department and other admins)
--
- Deadline:
- Officially 60 days after the 28/02/2017
- BUT will have to be over for the Review